| |
|
Multiple Screens for
Diverse Applications at Kumba’s Sishen Expansion
Project
The global demand for iron ore
resources which resulted in Kumba’s Sishen Expansion
Project (SEP), will see the extraction of an
additional 10 million tons of iron ore from this
Northern Cape operation. This will bring Kumba’s
total extraction volume to 38 million tons by 2009.
A critical aspect in determining the successful
implementation of the diverse range of screens for
the multitude of applications throughout the plant
was the close relationship fostered between Kumba
Resources, the screen cloth supplier and the various
OEMs on site. |
Pulling it all together
Joest is a wholly owned South African company which holds
the licence and distributorship for Joest technology in sub
Saharan Africa. The company manufactures and supplies
vibratory screens and feeders to the bulk materials
industry.
Operating out of premises in Spartan, Joest has the
necessary resources to design, manufacture and test
equipment at its facility. One of the primary
differentiators is the company’s ability to select the most
appropriate vibrating screen or feeder for a given
application.
“We would typically analyse the process
requirements and design the machine to suit the application,
resulting in better process efficiencies and throughput,”
Malcolm Skeen, sales director, Joest, says. “With this focus
on custom specific equipment, we were well positioned to be
able to offer SEP a cost efficient and viable solution.”
The company secured the full scope of supply in the crushing
and screening building at SEP. This included a Joest
secondary scalping screen, a secondary feeder and eight
tertiary feeders which feed the tertiary screens that were
supplied by Schenk Process.
The Joest secondary scalping screen is 3.6 metre wide and 10
metre long and is engineered to screen to 90 mm at 6 500
t/h. The secondary feeder and tertiary feeders are capable
of handling between 1 200 to 2 000 t/h and are 2.5 metre
wide and 4 metre long. The secondary feeder transfers
material into the tertiary crusher, and the tertiary
feeders, in turn feed the 3 metre wide by 9 metre long
Schenck screens cutting at 27 mm.
During the design stages, the Joest secondary scalping
screen, with a 43 ton vibrating mass, required in-depth
finite element analysis to ensure optimum strength to mass
ratio. “In addition, the metallurgical efficiency of screens
is determined by the mechanical characteristic of the screen
and this has to be factored into the machine from the start
and cannot be retroactively adjusted on the screen,” Skeen
says.
The secondary feeders had to be able to withstand
significant bunkers loads which were also taken into account
during the design and engineering of the feeder.
The jig beneficiation plant at SEP comprises eight modules
and each module consists of nine screens in the format of a
double deck primary vibrating screen of 3 x
6.1 metre, a 2.1 x 4.8 metre single deck secondary sizing
screen, four 1.8 metre wide x 4.88 metre long jig dewatering
screens and three 1.2 x 3 metre fines jig dewatering
screens. In total, Joest supplied 72 machines for the jig
beneficiation plant.
In addition to the SEP, Joest has supplied screen machines
to other projects in the Northern Cape including the ASSMANG
BKM Project and the company is considered the dominant
supplier into hard metal mining in this region.
Skeen says that Multotec polyurethane screen cloth panels
were selected for all screens on the plant. “The secondary
sizing screen is fitted with 0.8 x 8.8 mm Multotec Hi Flow
polyurethane screen panels and both the coarse jig
dewatering screens and the medium jig dewatering screens
have Multotec Hi-Flow panels, but with 3.5 x 9 mm and 0.6 x
8.8 mm slots respectively.” The fines jig has 0.63 x 8.8 mm
aperture Multotec Hi Flow panels.
“The Multotec Hi-Flow screening system offers maximum screen
surface area available for apertures as well as high open
area, high throughput and efficiency,” Skeen says. In
addition to this, the Multotec Saddle Top runners and T-Bar
Rail System was selected for the screens capable of
accepting such a system (48 off) in the jig beneficiation
plant as it significantly increases the lifespan of
vibrating screen support frames and screen panels.
“The Saddle Top system is a better solution in terms of
maintenance on the runner and wear interface between the
stringer and the panel. Similar variations are offered in
the marketplace but we believe that the Multotec system is
the most cost effective and definitely the best solution for
this particular application,” Skeen says.
The Multotec Saddle Top is a saddle that fastens to a
vertical laser cut flat-bar runner. This rail system
replaces the conventional angled runners on a vibrating
screen frame. Its major advantage is that when the fastening
holes become worn it is only necessary to replace the saddle
top itself and not the complete runner system. This can be
accomplished with semi-skilled labour.
Manufactured from polyurethane, the Multotec Saddle Top has
improved impact and abrasion resistance especially when
compared to conventional angled runners. The excellent wear
characteristics result in improved life as well as reduced
maintenance and downtime.
The 24 fine jig dewatering screens were unable to
accommodate Saddle Tops because of the nature of the deck
frame.
“The jig beneficiation plant was an expansion in our market
share in the screens business in that we typically supply
machines for the front end of the process, so to engineer
and supply screens for the downstream processes in
beneficiation proves that we are able to offers full scope
of screening solutions for a mining process,” Skeen
comments.
Dewatering bins
Grinaker-LTA Mechanical & Electrical’s Metals and Minerals
division secured the contract to fabricate, construct,
install and assist with commissioning of the dewatering bins
for the Sishen Expansion Project.
In total, 49 dewatering bins were supplied for the project
in a phased approach. Each dewatering bin comprised 30
compartments and these are fitted with a wedgewire screen.
The total length of each bin is about 60 metre and it is 14
metre high.
Material is transported via shuttle conveyor to the inlet
feed of the dewatering bin, and water is drained through the
sides of the dewatering bin which has a sloped angle of 32˚.
The water drains through the wedgewire panels into a
channel, while the product is gravity fed to a transfer
chute.
The inlet section of the dewatering bin has solid panels
while various wedgewire panel sizes were used at the outlet
end of the bin. These panels were individually tailored to
fit the configuration of the dewatering bin with the
majority having a surface area of 2 metre x 550 mm.
Fabrication of the dewatering bin formed only a portion of
Grinaker-LTA Mechanical & Electrical’s total scope of supply
on the SEP. The company’s new Metals and Minerals Division
secured two contracts at SEP.
“Our ability to provide a comprehensive multi-disciplinary
service and the expertise within our different operating
divisions has positioned us to provide a complete service
for this type of project,” Marius Botes, general manager
Grinaker-LTA Metals & Minerals, says.
The scope of the first contract involved the fabrication,
supply and erection of all structural steelwork, platework
and related items for the beneficiation and jig plant at the
SEP. It also covered the installation of all mechanical
items within the plant. Construction work was completed in
the second quarter of 2007.
The second contract involved the detailing, fabrication and
supply of the structural steelwork as well as the mechanical
installations for the conveyors and transfer towers between
the primary crusher and the run-of-mine (ROM) bed.
Multotec wedgewire screens, as used by Grinaker-LTA
Mechanical & Electrical on the SEP dewatering bins, are made
to tight tolerances of between 0 to -5 mm on the 10 metre
diameter unit. “Just as important is the profiling of the
wedgewire and the robustness of the screen deck itself,”
Botes says.
Generally, wedgewire is supplied in stainless steel, as this
ensures long life even in abrasive and corrosive
applications. The wedgewire screen decking is also designed
with high release angles to ensure minimal blinding and
pegging. The type and size of profile as well as the slot
width and materials are chosen to suit the mechanical and
process requirements of the screen of jig concerned and the
close tolerances on the aperture sizes ensure a uniform flow
rate and dewatering efficiency.
The wedgewire can also be supplied in exotic materials for
applications with varied chemical compositions if required.
As part of Multotec’s overall service, it offers in-house
Finite Element Analysis (FEA) prior to manufacturing, to
confirm that the steel support structure and flooring are
capable of meeting the full load bearing requirements.
Ultimate control
allmineral, acknowledged as the largest jig supplier in the
world, was also involved on the prestigious SEP. “The
process technology at SEP was developed specifically for
this application and is the heart of the entire project,”
Udo Busch, managing director of allmineral, says.
“One of the primary reasons SEP chose allmineral machines
was essentially because of the control system, which will
ensure optimum efficiency, recovery and grade,” Busch adds.
These alljig® machines are under-bed air pulsed jigs
ensuring a physically stable operation and optimal jigging
stroke with minimal energy consumption. Other alljigs® in
operation in South Africa are at Cato Ridge in a manganese
metal from slag recovery plant as well as an installation in
Steelpoort for the recovery of chrome-metal from slag.
“Although we have almost 400 jigs in operation globally,
this order for SEP is the largest single supply worldwide,”
Busch adds.
Busch explains that a pilot plant was bought by SEP and test
work was conducted over a period of two years prior to the
project. “Following on the data from the pilot plant test
work we, in co-operation and in consultation with the
metallurgists from Sishen and Kumba Resources, refined the
jigging process, especially with regard to the control
system, ensuring optimum recoveries at the most appropriate
grade.”
SEP ordered 18 jigging machines from allmineral in October
2005 and subsequently placed an order for an additional six
alljig® systems. The first of six modules were installed and
commissioned at the end of 2007 with the balance due during
the second quarter of 2008.
Phase IA comprised the supply of six identical jigs each for
the coarse, medium and fine ores with a total throughput of
1 000 t/h. Each module was designed to take the specified
export product grade requirements into account. The first
and biggest jig, the 4 metre wide coarse jig, was assembled
complete with gate discharge system and deck in the local
workshop prior to delivery in order to minimise the erection
time on site as well as ensure that any possible assembly
problems had been eliminated.
Screening solution
The Multotec screen cloth panels for the entire project were
delivered in a phased approach to the various OEMs over a
three month period. In addition to the supply of the screen
panels, Multotec also concluded a maintenance contract with
Kumba for all the polyurethane screening media installed on
the SEP. This is on a rate per ton basis which will ensure
optimum performance of the screens for the mine. Multotec
maintenance teams are based on site at SEP and are
responsible for monitoring and replacing panels as required.
Monitoring
Monitoring of the screen panels is performed using the
Multotec in-house developed Hawkeye Monitoring Programme
which effectively monitors screen maintenance processes to
provide guaranteed efficiency.
Hawkeye is a Web based application, accessible anywhere in
the world, which offers the user an easy-to-use interface to
allow accurate and efficient recording of maintenance
activities. These entries are stored in a database, and can
be called up as required in a number of ways so as to zero
in on what is actually happening on the screen. Another
critical benefit is that screen panel life expectancy can be
determined.
“At the end of the day, the success of the project was
achieved through superior teamwork and meeting exacting
customer demands,” Skeen concludes. |
|